Try OpenEdge Now
skip to main content
Developing BPM Applications with Developer Studio
Working with Business Calendar : Using the Business Calendar tool : Overwriting a schedule
 

Overwriting a schedule

You can overwrite a schedule for selected day (or days) with another schedule.
1. Drag across the calendar days, whose schedule is to be overwritten.
2. From the Select Schedule dialog box, select any schedule from the Schedule drop-down list.
3. Click OK to apply the schedule to the selected days.
Note: You can apply a different schedule to each day of the calendar year. You can also use the same schedules for other calendars created using the Business Calendar tool (see Managing calendars).