Changing the workstep performer

You can change the assigned performer of an activity workstep to any other performer or performer type.
1. Right-click an Activity, Adapter, or Subprocess workstep and then select the Change Performer option to open the Change Performer dialog box.
2. From any of the listed performer types, select a specific performer and click OK.
You can also change the performer through the Activity or Subprocess workstep’s Properties view. This procedure, however, only enables you to change to a performer of the same performer type.